Why are Irish data centre MEP designs getting harder to coordinate?
Data centres used 23% of Ireland’s metered electricity in 2025 (Computing, citing CSO data). In December 2025 the CRU published its decision on large energy users (CRU/2025236): new connections of 10 MVA and above need dispatchable generation or storage, on site or nearby, matching the connection capacity, plus 80% renewable matching (DLA Piper, Mason Hayes & Curran). Dublin’s grid is described as extremely tight, which pushes new sites to the regions (William Fry).
Our reading of what that means for the M&E design team: a data centre is no longer a set of data halls with a utility connection. It is data halls plus an energy centre, generator and battery compounds, more HV and MV switchgear, more fuel storage and longer cable routes, often on a greenfield regional site. Every one of those adds plant that has to fit, be maintained and be connected. That is coordination work, and most of it has to be settled at design stage, before a contractor prices it.
What gets coordinated in a data centre MEP model?
White space (data halls)
- Cooling units (CRAH or CRAC units, fan walls or in-row coolers) and their chilled water or refrigerant connections.
- Hot-aisle or cold-aisle containment and the clear zones it needs above and around the racks.
- Overhead busbar, power cable tray and data containment, with the separation your design requires.
- Fire detection (including aspirating systems), gas suppression or pre-action sprinkler pipework, lighting and leak detection.
Grey space and plant
- UPS and battery rooms, LV switchrooms, MV/HV switchgear and transformers.
- Chillers, dry coolers, pump rooms and the pipework headers between them.
- Generator yards, fuel storage and distribution, and battery energy storage compounds.
- Corridors and risers where power, cooling and fire services all compete for the same space.
We model all of this in Revit, federate it with the architectural and structural models in Navisworks, and coordinate it to the LOD your stage needs, typically LOD 300 at developed design and LOD 350 at technical design. Our article on BIM clash detection for data centres covers the clash side in more depth.
Where do data centre coordination problems usually come from?
| Area | Typical conflict | What we check at design stage |
|---|---|---|
| Data hall ceiling void | Busbar, cable tray, containment and sprinkler or suppression pipework stacked in the same zone | Layered service zones, access to busbar tap-offs, clearance to containment |
| Cooling distribution | Chilled water mains crossing power routes; no room for valves, flushing points or expansion | Valve access, drain and vent positions, routes that keep water away from electrical rooms where the design requires |
| Electrical rooms | Switchgear, UPS and batteries without withdrawal, cable entry or maintenance space | Front and rear clearances, cable entry routes, door and replacement paths |
| Energy centre and yards | Generators, fuel, transformers and battery storage competing for yard space and cable routes | Plant footprints, maintenance and delivery access, HV/LV route coordination with civils |
| Repeated halls | A fix made in one hall not carried into the others | Typical-hall modelling, so a change is made once and propagates |
Qualitative, based on our coordination experience. Requirements such as service separation and clearances come from your design and the client’s standards; we coordinate to them, we do not set them.
How does design-stage coordination work for a consultant?
- Intake: we review your engineering inputs (schematics, mark-ups, load and room data sheets), the architectural and structural models and the BEP, and agree the clash matrix and tolerances.
- Modelling: systems are modelled in your Revit template, with typical halls set up so repeated content stays consistent.
- Federation and clash runs: Navisworks tests across all disciplines, reviewed manually so the issue list holds real problems rather than noise.
- Resolution: each issue gets a proposed fix and goes to your engineer for a decision. We do not change design parameters without your agreement.
- Output: a coordinated model, combined services drawings, builder’s work openings and clash reports, issued through your CDE.
Cooling and power deserve special attention because their failures surface late. See data centre cooling system coordination and high-density power distribution.
Should you hire, outsource or use an offshore bureau for data centre modelling?
Data centre work arrives in large, intense packages. Hiring for the peak means carrying the cost afterwards: a Dublin BIM coordinator with five or more years of experience is listed at €60,000 to €80,000 (Morgan McKinley 2026), before employer PRSI of 11.40% from October 2026 (BrightSG). An offshore bureau may charge less per hour, but data centre models are where treating engineering as drafting fails most visibly (MVN): the geometry clears, but the valve cannot be reached or the switchgear cannot be withdrawn.
We sit between the two. The team is EU-based and one hour ahead of Dublin. Our founder’s MEPF site experience dates back to 2009 and includes data centre projects in Dublin. And the work is quoted as a fixed price per package, so the cost stops when the package does. For how Irish costs compare with other European hubs, see data centre MEP costs across Europe.
How do repeated data halls change the modelling approach?
Most campuses repeat a hall design several times, and the risk is that the model drifts as each copy gets its own fixes. We set up typical-hall content so a coordination change is made once and carried into every instance, keep shared parameters consistent so schedules and quantities stay reliable, and automate repetitive tasks where it saves time without hiding decisions. Because the halls are consistent, the clash review can focus on the places that are different: the ends of halls, the connections to the plant and the corridors.
How is a data centre client’s information protected?
Data centre clients are cautious about layouts, and rightly so. We sign your NDA before any files are shared, work inside your common data environment (Autodesk Construction Cloud or BIM 360) so that models stay in your hub, and handle data under GDPR as an EU business. We follow the security requirements in your BEP, in line with ISO 19650-5 (BIM+). Our trust and security page sets out the detail, including what is available on request.
How does the fixed-price pilot work?
Data centre work is too important to hand over on trust. Start with a small, real piece of the design: one data hall bay or one plant room.
- One data hall bay or one plant roomyour models, your template
- About 10 working daysfrom complete inputs to coordinated model
- Fixed quote in 48 hoursagreed before any work starts
You get a coordinated Revit model in your template, a Navisworks clash report with a proposed resolution for every issue and a sample combined services drawing. Review it with your own engineers before committing to a larger package.
Request a pilot quoteFrequently asked questions
What is data centre MEP BIM coordination?
It is the process of modelling the mechanical, electrical, fire protection and controls services of a data centre in BIM and resolving the conflicts between them, and with the structure and architecture, before construction. At design stage it covers the data halls, electrical rooms, plant, yards and energy centre.
How does the CRU connection policy affect MEP design?
The CRU decision of December 2025 requires new large connections of 10 MVA and above to provide dispatchable generation or storage matching the connection capacity. In practice that adds energy centre, generator, fuel and battery storage plant that has to be designed and coordinated alongside the data halls.
Do you work for consultants or contractors on data centres?
Our main focus is design-stage coordination for building services consultants. We also support MEP design-and-build contractors with coordination, combined services drawings and builder's work openings.
What LOD do you model data centres to?
We model to the LOD your stage and BEP require, typically LOD 300 at developed design and LOD 350 at technical design. We can go further, up to LOD 500, where a project needs it.
Can you keep our layouts confidential?
Yes. We sign your NDA before files are shared, work inside your own CDE so models stay in your hub, and handle data under GDPR as an EU business.
How long does a data centre pilot take?
A pilot of one data hall bay or one plant room typically takes about 10 working days from complete inputs, and we give you a fixed quote within 48 hours.
Sources
- Computing — Irish data centres use a quarter of electricity (CSO data), accessed October 2026.
- DLA Piper — New Irish large energy users connection policy, accessed October 2026.
- Mason Hayes & Curran — CRU sets out new rules for data centre connections, accessed October 2026.
- William Fry — Ireland’s data centre connections back online, accessed October 2026.
- Morgan McKinley — Ireland construction salary guide 2026, accessed October 2026.
- BrightSG — My Future Fund and PRSI, Budget 2026, accessed October 2026.
- MVN — Why offshore MEP design outsourcing fails, accessed October 2026.
- BIM+ — Understanding ISO 19650-5, accessed October 2026.